\def \CapstoneTeamName{Automated Fenceless Grazing}
|
|
|
|
\def \CapstoneTeamNumber{CS3}
|
|
|
|
\def \GroupMemberOne{Ryan Alder}
|
|
|
|
\def \GroupMemberTwo{Danila Fedorin}
|
|
|
|
\def \GroupMemberThree{Matthew Sessions}
|
|
|
|
\def \CapstoneProjectName{Automated Fenceless Grazing}
|
|
|
|
\def \CapstoneSponsorCompany{Oregon State University}
|
|
|
|
\def \CapstoneSponsorPerson{Bechir Hamdaoui}
|
|
|
|
\def \DocType{Retrospective}
|
|
|
|
|
|
|
|
\newcommand{\NameSigPair}[1]{\par
|
|
|
|
\makebox[2.75in][r]{#1} \hfil \makebox[3.25in]{\makebox[2.25in]{\hrulefill} \hfill \makebox[.75in]{\hrulefill}}
|
|
|
|
\par\vspace{-12pt} \textit{\tiny\noindent
|
|
|
|
\makebox[2.75in]{} \hfil \makebox[3.25in]{\makebox[2.25in][r]{Signature} \hfill \makebox[.75in][r]{Date}}}}
|
|
|
|
|
|
|
|
\begin{document}
|
|
|
|
|
|
|
|
\begin{titlepage}
|
|
|
|
\pagenumbering{gobble}
|
|
|
|
\begin{singlespace}
|
|
|
|
% 4. If you have a logo, use this includegraphics command to put it on the coversheet.
|
|
|
|
%\includegraphics[height=4cm]{CompanyLogo}
|
|
|
|
\par\vspace{.2in}
|
|
|
|
\centering
|
|
|
|
\scshape{
|
|
|
|
\huge CS Capstone \DocType \par
|
|
|
|
{\large\today}\par
|
|
|
|
\vspace{.5in}
|
|
|
|
\textbf{\Huge\CapstoneProjectName}\par
|
|
|
|
\vfill
|
|
|
|
{\large Prepared for}\par
|
|
|
|
\Huge \CapstoneSponsorCompany\par
|
|
|
|
\vspace{5pt}
|
|
|
|
{\large Prepared by }\par
|
|
|
|
Group\CapstoneTeamNumber\par
|
|
|
|
% 5. comment out the line below this one if you do not wish to name your team
|
|
|
|
\CapstoneTeamName\par
|
|
|
|
\vspace{25pt}
|
|
|
|
}
|
|
|
|
\begin{abstract}
|
|
|
|
The Fenceless Grazing Collar system aims to reduce the amount of work
|
|
|
|
needed by farmers to keep herds of grazing animals. The project
|
|
|
|
will be implemented using the LoRa wireless communication protocol to allow
|
|
|
|
for long-range interaction between animal-worn collars and a gateway device.
|
|
|
|
The gateway device will also provide an HTTP-based JSON API to apply configuration
|
|
|
|
changes to collars through an application built for Android mobile devices.
|
|
|
|
The MariaDB SQL database management system will be used to store the data
|
|
|
|
received from the collar for viewing and analysis.
|
|
|
|
\end{abstract}
|
|
|
|
\end{singlespace}
|
|
|
|
\end{titlepage}
|
|
|
|
|
|
|
|
\pagebreak
|
|
|
|
\tableofcontents
|
|
|
|
|
|
|
|
\pagebreak
|
|
|
|
|
|
|
|
\section{Introduction}
|
2019-12-05 22:22:12 -08:00
|
|
|
% TODO briefly recap the project purposes and goals
|
2019-12-06 00:07:22 -08:00
|
|
|
This document describes the current state, problems, and future
|
|
|
|
plans of the Fenceless Grazing Collars project. The FGC system's
|
|
|
|
purpose is to reduce the amount of manual labor required for herding
|
|
|
|
large numbers of livestock. The system does so by placing GPS-equipped
|
|
|
|
collars onto individual animals, and producing a negative stimulus
|
|
|
|
(either auditory or electrical) to discourage the animals from leaving
|
|
|
|
user-configured grazing areas. The goal of the project is to
|
|
|
|
provide a reliable, cost-effective, and accessible replacement
|
|
|
|
for manual farmer labor.
|
2019-12-05 22:22:12 -08:00
|
|
|
|
|
|
|
\section{Current Project State}
|
|
|
|
% TODO describe where you are currently on the project
|
2019-12-06 00:07:22 -08:00
|
|
|
At present, the initial design of the project is complete. The project's structure
|
|
|
|
lends itself very well to division among the three group members, and all
|
|
|
|
team members' responsibilities have been explicitly defined and agreed upon.
|
|
|
|
The team members all successfully researched the components of the project that
|
|
|
|
they are responsible for, and their research has been incorporated into a thorough
|
|
|
|
design document.
|
|
|
|
|
|
|
|
Both the technical reviews produced by the individual team members and the
|
|
|
|
design document have been validated by the client, and there is consensus
|
|
|
|
between the team and the client regarding future plans.
|
|
|
|
|
|
|
|
With the initial design complete, the project is ready to move into the
|
|
|
|
implementation stage, with the exception of funding: once the department
|
|
|
|
provides the team with funding required to purchase the hardware components
|
|
|
|
specified in the design document, work can begin on implementing an initial
|
|
|
|
prototype.
|
2019-12-05 22:22:12 -08:00
|
|
|
|
|
|
|
\section{Problems}
|
|
|
|
% TODO describe any problems that have impeded our progress, with any solutions we have
|
|
|
|
|
2019-12-06 00:07:22 -08:00
|
|
|
\section{Weekly Progress}
|
|
|
|
% TODO The document should include a detailed, week-by-week summary of activities,
|
|
|
|
% problems, solutions, and the like (consider using your blogs to inform this report).
|
|
|
|
% The report should not include more than a summary of any bigger documents you produced
|
|
|
|
This section contains the summary of each week of the Fall term during which the
|
|
|
|
project was active.
|
|
|
|
|
|
|
|
\subsection{Week 3}
|
|
|
|
This was the first week during which we tracked progress. It consisted largely
|
|
|
|
of drafting, submitting, and merging
|
|
|
|
the requirements document and problem statements. This went smoothly; each team member
|
|
|
|
felt confident in their understanding of the project's requirements and the
|
|
|
|
problem it is solving, likely because our group was offered the project in
|
|
|
|
the summer before the class had started. The only foreseeable problems at
|
|
|
|
this point is the difficulty in scheduling a semi-regular meeting with the
|
|
|
|
client: each group member, and the client themselves, are exceptionally
|
|
|
|
busy during this academic term, and on most week, no single time works
|
|
|
|
for every person. This problem is not significant at this point, however,
|
|
|
|
because the team has enough information to work for the time being.
|
|
|
|
|
|
|
|
\emph{Note: At this point, some members of the team received lower scores
|
|
|
|
than expected for certain submissions. Since the content of the various
|
|
|
|
submissions was agreed upon by each team member, the variance in
|
|
|
|
the received scores was unexpected and was listed as a "problem". However,
|
|
|
|
this did not impact the project itself, since one of the submissions
|
|
|
|
received full points.}
|
|
|
|
|
|
|
|
|
|
|
|
\subsection{Week 4}
|
|
|
|
This week consisted largely of revisions to the requirements document and
|
|
|
|
independent research. Team roles have been decided as early as this week:
|
|
|
|
each team member has a particular "strong suit", and will be playing
|
|
|
|
to their strengths in implementing this project. Since team roles have
|
|
|
|
been assigned, and since the team already has a vague understanding
|
|
|
|
of what components the project will consist of, members are eager to purchase
|
|
|
|
hardware and begin tinkering. However, a meeting has not yet been established
|
|
|
|
with the client at this point, and the matter of funding has not yet been
|
|
|
|
decided. It is not clear at this point who will be financing the hardware
|
|
|
|
required for the project.
|
|
|
|
|
|
|
|
\subsection{Week 5}
|
|
|
|
During this week, the source of funding was somewhat elucidated by a team
|
|
|
|
member's individual meeting with the client. The team was informed
|
|
|
|
that \$300 has been set aside for each Senior Capstone team to help with funding.
|
|
|
|
The team's TA was asked about this, but was not aware of the details, and
|
|
|
|
offered to contact Dr. Winters.
|
|
|
|
|
|
|
|
While there is not yet an exact date for a meeting with the client, one
|
|
|
|
is soon to be established. Each group member and the client provided the
|
|
|
|
times during which they are available, revealing that there were no
|
|
|
|
time slots during which each individual was available to meet. As such,
|
|
|
|
one of the group members will likely skip this meeting, and the rest
|
|
|
|
of the group members will fill them in.
|
|
|
|
|
|
|
|
In preparation for the client meeting, team members have been doing further
|
|
|
|
research into their components of the project. This coincides well with the
|
|
|
|
first drafts of the technical review, which require exactly the type of
|
|
|
|
research that the team will present to the client in the meeting.
|
|
|
|
|
|
|
|
\subsection{Week 6}
|
|
|
|
The highlight of this week was the first meeting with the client. This meeting
|
|
|
|
was scheduled last-minute, but went very well. The team's plan and the client's
|
|
|
|
expectations were not significantly different.
|
|
|
|
|
2019-12-05 22:22:12 -08:00
|
|
|
\section{Retrospective}
|
|
|
|
% TODO add retrospective
|
|
|
|
% positives column: anything good that happened
|
|
|
|
% deltas column: changes that need to be implemented
|
|
|
|
% actions column: specific actions that will be implemented in order to create the necessary changes
|