@ -56,4 +56,25 @@ Additionally, as described in the progress section, we have scheduled
a meeting with our advisor, and plan on purchasing components shortly
after the meeting takes place.
\section{Week 5}
\subsection{Progress}
We have constructed preliminary designs for the various nodes and gateways
that we will have set up throughout fields. With this, we also determined
the components that we may need for the project - after a little more
discussion with our advisor, we will be able to proceed with the purchases.
Additionally, we have contacted our advisor to schedule a weekly
meeting, and are waiting on a response.
\subsection{Problems}
We are as yet unsure about the source of funding for the purchase of our
hardware. We have contacted the TA, and are waiting for more information.
No other issues have come up.
\subsection{Plan}
The plan is to continue doing the class assignments, while at the same
time doing additional research into the hardware components and mechanics
of our project. We will stick with the prescribed class schedule otherwise,
and continue to do some work on an assignment every day. The next
assignment up is the first draft of the tech review.