@ -188,7 +188,7 @@ research that the team will present to the client in the meeting.
|
||||
\subsection{Week 6}
|
||||
The highlight of this week was the first meeting with the client. This meeting
|
||||
was scheduled last-minute, but went very well. The team's plan and the client's
|
||||
expectations were not significantly different. To accomodate the team and
|
||||
expectations were not significantly different. To accommodate the team and
|
||||
the client's busy schedule, meetings were agreed to be bi-weekly, and made
|
||||
optional (to prevent wasted time in the event that no new information is
|
||||
required by the group). During this week, team members wanted to begin
|
||||
@ -208,7 +208,7 @@ in the second draft. The first draft was submitted on time and with no other iss
|
||||
|
||||
Since the team was busy with the creation of the design (and the design document),
|
||||
the issue of funding was not significant at this time. The group member responsible
|
||||
for the hardware simulated some of the components of the initial design, in order
|
||||
for the hardware simulated some components of the initial design, in order
|
||||
to explore the implementation of the project. However, no significant insight
|
||||
was gained from this, with the exception of familiarity with the tooling.
|
||||
|
||||
@ -224,11 +224,11 @@ of the document, which were promptly corrected. At this point, the document was
|
||||
complete with the exception of UML diagrams, which were scheduled to be inserted
|
||||
during the weekened.
|
||||
Other than the medical emergency and the design document, no significant problems
|
||||
or progress occured this week.
|
||||
or progress occurred this week.
|
||||
|
||||
\subsection{Week 9}
|
||||
This was a short week which ended in Thanksgiving, and no significant changes
|
||||
to the state of the project occured at this time. The team submitted all the
|
||||
to the state of the project occurred at this time. The team submitted all the
|
||||
generated documentation to the client / advisor, but did not receive a
|
||||
response during this week. No issues were encountered during this time.
|
||||
|
||||
|